NORTH KEENE SUBSTATION Substation
NORTH KEENE SUBSTATION |
|
---|---|
Client | Eversource Energy |
Completion Date | 2016 |
Location | New Hampshire |
Completed by | E.S. Boulos Company |
The E.S. Boulos team constructed a new greenfield 115/12.74kV substation to increase load serving capability in the Keene area. They installed two 115kV line terminals to accept “looping in and out” of the L163 115kV transmission line; two 115kV circuit breakers feeding a 30MVA transformer; and a control house to accommodate traditional relaying and control equipment.
The new 115kV/12.47kV transformer will feed five distribution feeders via bus tied with a breaker.